Abstract:
Power Grid Company of Bangladesh (pGCB) is created under the restructuring process of Power
Sector in Bangladesh. This report is based on our internship work in Power Grid Company of
Bangladesh at Manik Nagar branch. A power system has three basic segments, i.e. power
generation, power transmission and power distribution. Basically Power Grid Company of
Bangladesh deals with transmission part only. It primarily focuses on different processes of
power transmission in power grid. We were introduced with various equipment of Power Grid,
such as Relay, Circuit Breaker, Power transformer, Bus bars, Disconnector, Wave trap, Cable,
DC battery.
We worked at PGCB as intern for 80 hours. Each day our activities were divided into three parts.
yustly our supervisor talked to us about the theory behind our day topic. Then we visited the grid
with our supervisor to relate theory with practical implementation. Finally we visited the grid
again to gather ourselves information about the equipment of that day.
Here we learned about power transmission and the behavior of various equipment used in grids.
This report contains a detail description about some of these equipments. As we did not complete
any major course related to power prior to doing the internship, we had to face hurdles. It would
be beneficial and better for us if we had completed the courses Switchgear, Power Station and
Power Electronics.
Description:
This internship submitted in partial fulfillment of the requirements for the degree of B.Sc in Electrical and Electronic Engineering of East West University, Dhaka, Bangladesh.